St. Mary’s Elementary School Restoration

Client


St. Marry's Elementary School
931 South Byers Street
Joplin, Mo 64801

Cost

$1.2 million

Project Description

$1.25 million Restoration/Construction:  2 story, 12,000 sf, 100-year-old building with concrete/masonry construction.  Project included demolition then rehabilitation from vacant shell to use as code compliant private catholic elementary school.  As General Contractor, NGC provided directed this rehabilitation from project design to final construction.  This fast paced design build project following the Joplin tornado went from design to occupancy in 8 weeks.
 

Project Role

General Contractor, Restoration, Construction

Project Attributes

May 22nd, 2011 Saint Mary’s Catholic School was destroyed by an EF5 Tornado.
Neal Group Construction restored a new space for the school in 8 weeks.